WHR Project for Sharjah Cement Plant Passing the Performance Guarantee Test
Release time:
2013-11-26
Recently, the performance guarantee test of 8.5MW waste heat recovery power plant supplied by Nanjing Kesen Kenen Environment & Energy Co.,Ltd (NKK),China, for 2233t/d and 4102t/d cement production lines in Sharjah Cement Factory, has been carried out and passed successfully.
The WHR project was a complete EPC turn-key project, which only took 15 months from the effective date to synchronizing, created the shortest record of construction period compared with other similar projects abroad. The performance guarantee test which has been carried out successfully on March 23th, 2015 and exceeded the guarantee values, received high appraisal and cash bonus from the owner, who also issued the PAC certificate on the same day.
Our WHR team always adhered to the business philosophy of "building a project, setting up a monument" through the whole project, which fully demonstrated the excellent executive capacity of our company for waste heat recovery power plant projects. The whole plant was successfully handed over to the owner which enhances the brand influence of NKK in the international waste heat recovery market.