The WHR power generation project of Huaxin Chenzhou Cement Co., Ltd. was formally entered the performance test period on April 1st, 2010.
Release time:
2010-06-28
On April 1st, 2010, the WHR power generation project of Huaxin Chenzhou Cement Co., Ltd. was formally entered the performance test period. It’s a 5000t/d cement clinker production line with 9MW steam turbine generator of low-temperature WHR power generation project

+86 025-68082504
marketing@njkskn.com
Messages